Construction Journal for May 29, 2008
Thursday, May 29th, 2008May 29, 2008
Construction of major elements of the park continues at rapid pace.
Third floor rooms have received wall and ceiling finishes, final painting, installation of tub tiling is underway and bathroom floor tiling is complete. Doors are being installed. Hallway walls are finished and painted.
Stone wainscotting is being installed around the building and the concrete siding is being installed.
The maintenance building is nearing completion and the golf superintendent is moving in equipment. The clubhouse has been framed and is being dry-walled.
![]() |
![]() |